Punch list
Repair cracked terrazzo tile at main entry threshold
Two tiles cracked during scissor-lift move. Match existing aggregate.
Adjust automatic door operator closing speed
Closing faster than ADA sweep time. Operator manual on site.
Touch up drywall scuffs behind reception desk
Replace flickering downlight, ceiling grid C4
Driver swapped Aug 26. Burn-in verified overnight.
Reset misaligned rubber base trim, north corridor
Patch and paint ceiling water stain, room 214
Source leak repaired Aug 24. Confirm stain does not bleed through primer.
Rebalance VAV box serving rooms 210 through 216
Rooms reading 4 degrees over setpoint. Requires TAB contractor.
Re-caulk window sill joints, rooms 211 and 213
Door 216 latch does not engage strike plate
Strike shimmed and re-mortised. Verified by superintendent Aug 30.
Install missing cover plate, duplex outlet room 212
Re-seam lifting carpet tile at corridor transition strip
Grind and refinish uneven concrete at stair 2 landing
Trip hazard flagged by inspector. Lip measures 3/8 inch.
Remove paint overspray on window glazing, room 227
Re-secure exit sign hanging loose above door 220
Remounted to structure with threaded rod. Fire marshal sign-off pending.
Seal flashing gap at parapet, northeast corner
Interim membrane patch installed. Permanent counterflashing on order.
Relocate splash block, downspout discharges onto walkway
Regrade mulch bed away from foundation, south side
Replace cracked pane, storefront panel SF-3
Glass on 2-week lead. Panel taped and coned in the meantime.